In an unprecedented move, the oil ministry has sanctioned taking  "scrupulous" action against Reliance Industries for natural gas output  from its KG-D6 fields falling below the target. Contrary to the Production Sharing Contract (PSC), the ministry has  decided to disallow expenditure                 
Sources privy to the decision, taken by the ministry earlier this  month, said that based on the Solicitor General's opinion, which was  concurred by law minister Salman Khurshid, $1.85 billion -- out of the  $5.694 billion investment already made -- will be disallowed and  arbitration initiated to recover that from RIL.
Oil minister S Jaipal Reddy on November 9 instructed that "scrupulous" action may be taken against RIL.
Sub-surface issues like fall in pressure and water ingress have led  to fall in output at D1&D3 from 54 million standard cubic meters per  day, achieved in March 2010, to under 35 mmscmd currently instead of  rising to the targetted 61.88 mmscmd.
As per the PSC, an operator has right to recoup or recover 100% of  the expenditure he had incurred on finding and producing from the  revenues earned from sale of oil and gas before profits are split with  the government.
Such expenditure is approved by the government not once but twice --  first at the time of approving field development plan and then every  year at the time of approving annual budget for the fields.
And to alter this cost recovery, an amendment to the PSC is required which can be done only by the Parliament.
Sources said the ministry's decision is unprecedented because it was  accepted world-over that field behaviour is something that cannot be  accurately predicted and operators cannot be held responsible for  variations as evident from several fields of state-owned Oil and Natural  Gas Corp (ONGC) that missed targets by miles.
Numaligarh Refinery was built and refineries at Bongaigaon and  Barauni expanded in late 1980s based on projection of 11-12 million tons  of output from Assam fields of ONGC and Oil India. ONGC's output never  crossed 1.5 million tons against a target of 6-7 million tons, while OIL  was better off producing 3 million tons as compared to 5 million tons  target.
The shortfall was made up by diverting crude oil from eastern offshore Ravva fields.
Also, gas out from ONGC's western offshore field being way off the  target led to the nation's first trunk pipeline from Hazira to  Jagdishpur (HBJ) running half empty for years. ONGC's Neelam field also  produced only one-third of the targeted oil.
RIL had in September warned Oil Ministry of legal action saying the attempt to limit cost-recovery is illegal and ultra vires.
"If the PSC were indeed to be re-written to link cost recovery to  levels of production, it would also have to include provisions for  allowing the contractor (RIL) to recover costs in excess of his  investment in case he were to achieve a rate of production higher than  that estimated at the time of capex approval," RIL senior vice-president  (Commercial) B Ganguly had written to the ministry on September 16.
Sources said the oil ministry is basing its action on Solicitor  General of India's opinion that RIL should not be allowed to recover the  cost of facilities that remain underutilised due to lower than  anticipated output at its KG-D6 gas field.
SGI Rohinton F Nariman had in  August opined that "the  cost/expenditure incurred in constructing production/processing  facilities and pipelines that are currently underutilised/have excess  capacity cannot be recovered".
"There is no provision under the Production Sharing Contract (PSC)  that can limit cost-recovery to either production levels achieved by a  contractor or to the extent that facilities are utilised under a  development plan at any given point of time," RIL had written to oil  ministry.
The Initial Field Development Plan (FDP) for the D1 and D3 gas fields  in the KG-DWN-98/3 block (KG-D6) envisaged a capex of $2.47 billion at a  peak production rate of 40 mmcmd from 14 wells.
Subsequently, RIL submitted an addendum saying the size of the gas  reserves was twice the estimate of 5.32 tcf in the initial plan, at 11.3  trillion cubic feet. It proposed a $8.835 billion capex over two phases  and envisaged a peak output of 80 mmcmd from 31 producing wells by  April, 2012.
Commercial gas production from the D1&D3 fields commenced from  April 1, 2009. In December, 2009, RIL tested its field production  facilities at their full rated capacity of 80 mmcmd, during which an  average gas rate of 77-80 mmcmd was maintained for a brief period of  three days. The output included nearly 8 mmscmd from MA oilfield in the  same block.
Sources said RIL has till now made $5.693 billion expenditure on  D1&D3 development out of which about $4.365 billion has been on  production facilities only. It has already recovered $5.258 billion up  to March 31, 2011.
